What does comunicação prévia com prazo mean in Portugal?
A comunicação prévia com prazo is the notification used to start using a building, or to change its use, when no recent licensed or notified works lead to it. You may use the building ten days after filing, unless the council rejects it or orders an inspection.
- Rests on
- RJUE, art. 4.º n.º 5, art. 62.º-B, art. 63.º, art. 64.º
- Law
- Decreto-Lei n.º 555/99 (RJUE), as republished by Decreto-Lei n.º 108/2026
- Version
- In force since 1 October 2026 (Decreto-Lei n.º 155-B/2026)
- Official text
- data.dre.pt/eli/dec-lei/108/2026/05/29/p/dre/pt/pdf
- Sources
- data.dre.pt/eli/dec-lei/108/2026/05/29/p/dre/pt/pdf
data.dre.pt/eli/dec-lei/155-b/2026/07/31/p/dre/pt/pdf
data.dre.pt/eli/declretif/29-a/2026/07/27/p/dre/pt/pdf - Checked
- 2026-11-05
What it means for the owner
- It is filed with a termo de responsabilidade on the permitted use and on the suitability of the building for its purpose (art. 63.º n.º 1).
- Within the ten days the council president may reject the filing, or order an inspection if there are serious signs that the building is not suitable (art. 64.º n.º 2).
- An inspection takes place within 15 days, by a committee of at least three technicians (art. 65.º n.º 1 and n.º 2).
- Some municipalities treat certain uses as operations with a large impact and may require land cessions (art. 62.º-B n.º 4).